FDOT weighing options for safety improvements at Highway 29 and Barrineau Park Road
- 6 days ago
- 1 min read

The Florida Department of Transportation is considering two options to improve safety at Highway 29 and Barrineau Park Road. One would install a traditional traffic signal while keeping the intersection largely as it is. The other would create a restricted crossing U-turn, or RCUT, using a concrete barrier to prevent Highway 196 traffic from crossing Highway 29 directly. Drivers would instead turn right and use a designated U-turn. Both designs are 60-percent complete, with final design expected in early 2027 and construction planned for 2027 and 2028. FDOT will hold a public meeting September 15th from 5:30 to 6:30 p.m. at Victory Assembly of God, with a virtual option also available.